Configuring the Pb Signaling Link

This describes how to configure a signaling link on the Pb interface. This link is responsible for the signaling transmission of PS service procedure control and Pb transmission resource management.

ScenarioBSC initial configuration and BSC capacity expansion
Mandatory/OptionalOptional. A Pb signaling link must be configured when the BSC is configured with an external PCU.
NOTE:

Each GMPS or GEPS can be configured with up to 64 Pb signaling links.

Prerequisite

The Pb interface E1/T1 is configured. For details, see Configuring the Pb Interface E1/T1.

Preparation

Table 1 Example of the data negotiated and planned for configuring the Pb signaling link

Parameter

Example

Source

Port No.

0

Negotiation with the peer

Timeslot No.

19

Negotiation with the peer

Procedure

  1. On the BSC6000 Local Maintenance Terminal, right-click GEIUP in the GMPS.

    NOTE:

    The configuration of a Pb signaling link can be started only on the GEIUP/GOIUP in the GMPS/GEPS.

  2. Choose Configure Pb Signaling Link from the shortcut menu. A dialog box is displayed, as shown in Figure 1.

    Figure 1 Configuring a Pb signaling link

  3. Click Add. A dialog box is displayed, as shown in Figure 2.

    Figure 2 Add Pb Signaling Link dialog box

  4. Set the parameters by referring to Table 1.
  5. Click OK to return to the dialog box, as shown in Figure 1.
  6. Click Finish. The addition of the Pb signaling link is complete.